The project involves the installation of a 5.5-meter deep sewer system in Jurien Bay, addressing challenges posed by a high water table and dewatering needs.

Contract Type: AwardedYear completed: 2024
Jurien Bay 225 Sewer System

Project Details

Heritage assessment
Conducting assessments to identify and protect any heritage sites.
Deep sewer install
Excavating and installing a 5.5-meter deep sewer line connecting in to a live connection.
Dewatering solutions
Implementing systems to manage high water table conditions effectively.
Excavation works
Using appropriate machinery for deep excavation in challenging conditions.

Project Challenges

High water table
Encountered a high water table that complicated excavation and required additional dewatering measures.
Existing Infrastructure
Navigated existing underground utilities that posed risks to installation and required careful planning using shoring boxes in congested areas.