Cheriton Road - Drainage
Gin Gin, Western Australia
Supply materials and bulk bill for storm water upgrade from the corner of Whakea Road heading north along Cheriton Road in Gin Gin enhancing the water flow capacity and improving mother natures balance for the residents of Gin Gin.
Contract Type: AwardedYear completed: 2024
Project Details
Project planning
Conduct a thorough assessment of the existing road conditions, Complying with working corridors and minimum interference with live flowing traffic.
Materials procurement
Source and arrange for the delivery of high-quality RCP Culverts, Box Culverts, Head walls, SEP lids, Gully grated lids and Manholes.
Quality Assurance
BYDA services located and marked prior to starting. As built and designed to drawings, Compaction test reports recorded.Photos provided for bedding, pipe lay.
Sustainable Practices
Using natural methods like mulch, jute mesh or vegetation t prevent erosion, reduce sediment in run off areas and protect nearby waterways.
Project Challenges
Optic Fibre
The storm water alignment was redesigned to maintain a minimum clearance of 1 mitre from the identified optic fibre.
Road traffic management
Managed ongoing traffic flow, implementing safety measures and temporary detours.
Traffic Management Plans
Encountered restricted access to certain sections of the road, hindering equipment movement and working under traffic management.