Gin Gin Storm Water

Gin Gin, Western Australia

The project involves installing 1,500 meters of V-drains to enhance stormwater management and drainage efficiency in the Gin Gin Shire.

Contract Type: AwardedYear completed: 2024
Gin Gin Storm Water

Project Details

Drainage installation
Laying out and installing V-drains across designated areas.
Excavation works
Utilising excavators for site preparation and trenching.
Material supply
Sourcing and supplying all necessary materials for the installation.
Bobcat utilisation
Using Bobcats for efficient handling and movement of materials.

Project Challenges

Equipment limitations
Managing operational efficiency with Bobcats and excavators in confined spaces.
Worker safety
Navigated existing underground utilities that posed risks to installation and required careful planning using shoring boxes in congested areas.
Traffic management
Navigating traffic disruptions and coordinating with local authorities for road management.
Access Issues
Limited access to certain areas affecting the deployment of equipment and materials.