We were engaged by Tracc Civil to widen Hale Road from Tonkin Highway to Welshpool Road East, enhancing road capacity and improving traffic flow.

Contract Type: Sub ContractorYear completed: 2021
Hale Road

Project Details

Project planning
Conduct a thorough assessment of the existing road conditions and prepare the site for widening activities.
Materials procurement
Source and arrange for the delivery of high- quality limestone and road base materials to the site.
Compaction
Ensure proper compaction of the placed materials to achieve the necessary stability and support for the road structure.
Grade adjustment
Adjust the final grade of the widened road to ensure proper drainage and alignment with existing road features.

Project Challenges

Inconsistent soil conditions
Dealt with varying soil types, impacting excavation and compaction efforts.
Utility conflicts
Navigated existing underground utilities that required careful management to avoid damage during widening.
Limited access points
Encountered restricted access to certain sections of the road, hindering equipment movement.
Road traffic management
Managed ongoing traffic flow, implementing safety measures and temporary detours.