Bellevue Metro Rail
Bellevue, Western Australia
We were engaged by Civcon to help support scopes of work in relation to the “metro rail Bellevue drainage upgrade” focusing on site preparation, pipe installation, backfilling, and inspection, ensuring compliance with engineering specifications and project standards throughout the process.
Contract Type: Sub ContractorYear completed: 2021
Project Details
Project planning
Conduct necessary site assessments and prepare the installation area, ensuring proper clearance and access for equipment and personnel.
Pipe installation
Safely install the 1200 mm diameter Enviros pipe, ensuring alignment, level, and connection integrity according to engineering specifications and industry standards.
Backfill and compaction
Properly backfill the trench with suitable material, ensuring adequate compaction to prevent future settling and maintain structural integrity.
Inspection
Conduct thorough inspections during and after installation to ensure compliance with project specifications and local regulations.
Project Challenges
Site conditions
Encountered unexpected ground conditions that required adjustments to our initial plans.
Resource availability
Faced challenges in the timely availability of materials and equipment, affecting project timelines.
Weather delays
Experienced delays due to adverse weather conditions impacting work schedules.
Coordination issues
Managed difficulties in communication and coordination with subcontractors, necessitating proactive problem-solving.